Checklist playbook · New product introduction

Medical Device NPI Checklist

A gate-by-gate launch playbook, from concept approval to the first shipment

Every check says who owns it, whether it's a requirement or good practice, and where it comes from, in current ISO 13485, QMSR and EU MDR terms. Tailor it to your device, track progress as you go, and finish with a case study of a launch that slipped five months.

  1. 1Concept8 checks
  2. 2Inputs8 checks
  3. 3Design freeze11 checks
  4. 4V&V11 checks
  5. 5Transfer14 checks
  6. 6Launch16 checks
Required traces to a standard or regulation Good practice prevents delays + Read more for tips and pitfalls
Notes

Gate names vary between companies; move checks to the gate in your own procedure where they fit. A gate is a business decision, while a design review is a quality record under ISO 13485, so keep them as separate records even if they share a meeting.[1] Ticks are saved in this browser only.

Fit it to your device

Tailor the checklist

Device
Features
US
EU

0 done

Gate 1

Concept approved

Is this a product worth developing, and do we know what it is for?

0 of 8
  1. RequiredRegulatoryR&DISO 13485 7.3.3[1]

    Risk, evidence, the regulatory pathway and every marketing claim depend on this wording.

    Read more
    Good practice
    Write the intended use and indications as separate statements, and list users (by training), patients, body sites and use environments explicitly. Have regulatory, clinical and marketing agree the wording before design inputs are written.
    Rule of thumb
    If marketing wants to claim it, it has to fit inside the indications. Write the claims you hope to make on day one and check them against the draft.
    Common pitfalls
    Indications that are broader than the evidence you can afford; vague user groups (“healthcare professionals”) that hide very different training levels; intended use rewritten late, after testing was planned around the old one.
    Evidence to show
    A controlled intended use and indications statement, with an approval record and a change history.
  2. RequiredRegulatory21 CFR Parts 3, 4, 807, 814 and 860; EU MDR Art. 1(8)–(9), 51–52, 117[2][3]

    The pathway (for example 510(k), De Novo or PMA in the US, or a conformity assessment route in the EU) sets the evidence you need and the earliest realistic launch date.

    Read more
    Good practice
    Map each launch market to its classification rule and route, and write down the assumption behind each choice. Revisit the map at every gate, because pathways and rules change.
    Rule of thumb
    Your pathway decides your evidence, and your evidence decides your schedule. Settle it before you commit a launch date.
    Common pitfalls
    Assuming EU classification mirrors the US one; choosing a 510(k) without a solid predicate; forgetting that software or accessories may be classified separately.
    Evidence to show
    A regulatory strategy document with the classification rationale for each market and the planned submission type.
  3. Added for your deviceGood practiceRegulatoryCommercialFDA CLIA test categorization[4]

    Test complexity decides which laboratories can run it, which shapes the market you can sell into.

    Read more
    Good practice
    Decide early which complexity category you need, because a waived test needs specific studies showing untrained users get accurate results.
    Rule of thumb
    If the market is clinics and pharmacies, plan for a CLIA waiver from the start.
    Common pitfalls
    Planning point-of-care sales for a test that will be categorized as moderate complexity.
    Evidence to show
    CLIA strategy and, where pursued, the waiver study plan.
  4. Good practiceRegulatoryFDA Q-Submission program[5]

    Feedback from FDA before you test is cheaper than an additional information request during review. See it go wrong in the case study below ↓

    Read more
    Good practice
    Compare candidate predicates on intended use, technology and performance before you pick one. Use a Pre-Submission for questions that would change your testing, such as novel test methods or clinical data needs.
    Rule of thumb
    Ask FDA the questions whose answers would change your test plan, not the ones you could answer from guidance.
    Common pitfalls
    Picking a predicate for convenience when its technology differs in ways that raise new questions; asking a Pre-Submission too late to act on the feedback; treating feedback as binding when the design later changes.
    Evidence to show
    Predicate comparison table; Pre-Submission package, FDA feedback and meeting minutes, with how each point was addressed.
  5. RequiredR&DISO 13485 7.3.3; IEC 62366-1[1][6]

    Needs observed in clinics and homes, not assumed in meetings, become the basis for design validation.

    Read more
    Good practice
    Observe users doing the real task in the real setting, including the awkward parts: gloves, poor lighting, interruptions, fatigue. Turn observations into needs written in the user’s terms, and keep the use specification as a controlled document.
    Rule of thumb
    If you haven’t watched at least a few real users do the task, your needs are guesses.
    Common pitfalls
    Needs collected only from key opinion leaders; a use specification that lists one “typical” user; needs written as solutions (“a touchscreen”) instead of outcomes.
    Evidence to show
    Use specification, user research records, and a list of user needs traced to design inputs and validation.
  6. RequiredQualityISO 14971 4.4[7]

    Acceptability criteria agreed before analysis keeps later risk decisions consistent and defensible.

    Read more
    Good practice
    Agree the acceptability criteria and the method for estimating probability and severity before any analysis, and get top management to approve the policy behind them.
    Rule of thumb
    Decide what “acceptable” means before you see your own numbers.
    Common pitfalls
    Criteria tweaked after the analysis so the results pass; a plan copied from another product with the wrong severity scale; no plan for collecting production and post-production information.
    Evidence to show
    Approved risk management plan, including acceptability criteria, review responsibilities and verification activities.
  7. RequiredR&DQualityISO 13485 7.3.2[1]

    The plan is a controlled record that gets updated as the project changes, not a slide made once for kickoff.

    Read more
    Good practice
    Name the phases, the reviews at each, who is responsible for what, and how R&D, quality, regulatory, operations and suppliers hand work to each other. Keep it under document control and update it when the project changes.
    Rule of thumb
    If the plan still matches the kickoff deck six months in, either the project is perfect or nobody is updating the plan.
    Common pitfalls
    A plan that is really just a Gantt chart; interfaces with the contract manufacturer missing; reviews named but never scheduled.
    Evidence to show
    Controlled design and development plan with revision history and evidence of updates at each gate.
  8. Good practiceCommercial

    Engineering trade-offs need a target cost and volume to be made well.

    Read more
    Good practice
    Agree a target cost, expected volumes and launch markets early, and treat them as inputs to engineering trade-offs, not just finance slides.
    Rule of thumb
    A design that meets every requirement but can’t be built at the target cost is not done.
    Common pitfalls
    Volume assumptions that never reach the supplier or tooling plans; cost targets set after the design is frozen.
    Evidence to show
    Approved business case, with the assumptions that engineering and operations used.
  9. Good practiceCommercial

    Customers often can’t buy a device they can’t get paid for, however good the clearance.

    Read more
    Good practice
    Check early whether existing codes and payment cover the device in each market, and what evidence payers will want, since that can shape the clinical study.
    Rule of thumb
    If nobody can bill for it, clearance won’t sell it.
    Common pitfalls
    Clinical studies designed for clearance only, then repeated for payers; assuming an existing code fits without checking.
    Evidence to show
    Market access plan with coding, coverage and evidence assumptions.

Gate 2

Design inputs approved

Do we know exactly what we are building, how we will prove it works, and who will make it?

0 of 8
  1. RequiredR&DISO 13485 7.3.3[1]

    A requirement nobody can test, or one that contradicts another, tends to surface during verification, the most expensive time to find it.

    Read more
    Good practice
    Write each input so it can be verified or validated, trace it to a user need, risk control or regulation, and review the set for conflicts and gaps before approving it.
    Rule of thumb
    If you can’t say how you’ll test a requirement, it isn’t finished.
    Common pitfalls
    Requirements that hide design choices; “TBD” values that stay open until verification; performance targets copied from a competitor’s brochure without knowing the test conditions.
    Evidence to show
    Approved design input document or requirements set, with trace links and the review record.
  2. RequiredQualityR&DISO 14971; IEC 62366-1[7][6]

    Early hazards drive requirements while the design can still change cheaply.

    Read more
    Good practice
    Start the hazard analysis from the intended use, the energy and materials involved, and the use-related tasks, and let it shape the requirements while they are still drafts.
    Rule of thumb
    Every severe hazard should already have a planned risk control by the time inputs are approved.
    Common pitfalls
    Hazard analysis done after the design, to document it rather than shape it; use errors left out because “training will cover it”; risk files that never connect to requirements.
    Evidence to show
    Preliminary hazard analysis and use-related risk analysis, with links to design inputs.
  3. RequiredR&DIEC 62304; FD&C Act section 524B[8][9]

    The class sets software process rigor, and a cyber device needs cybersecurity documentation in its submission.

    Read more
    Good practice
    Assign the software safety class from the hazards the software can contribute to, and decide early whether the device meets the definition of a cyber device. Both drive how much documentation and testing you’ll need.
    Rule of thumb
    Classify for the worst credible harm the software could contribute to, not the harm you hope hardware will prevent, unless that hardware control is independent and verified.
    Common pitfalls
    Assigning a low class to reduce paperwork, then finding a hazard that needs a higher one; ignoring third-party software; treating cybersecurity as a late add-on.
    Evidence to show
    Software development plan with the safety class and rationale; cybersecurity scope and threat model.
  4. RequiredRegulatoryISO 13485 7.3.3; EU MDR Art. 8–9[1][3]

    A late-discovered standard can add months of testing.

    Read more
    Good practice
    List the standards that apply to your device and markets, with the edition you will use, and check which are recognized by FDA or harmonized in the EU. Note transitions to new editions.
    Rule of thumb
    Check the edition, not just the standard number. Test labs and reviewers will.
    Common pitfalls
    Testing to an outdated edition; missing a collateral or particular standard; assuming a standard applies to everything when it covers only part of the system.
    Evidence to show
    Standards list with editions, applicability rationale and the test plan for each.
  5. Good practiceOperations

    Custom parts, tooling and sensors often take longer than the design work around them.

    Read more
    Good practice
    Identify parts with long lead times, single sources or custom tooling, and place orders or reservations early. Decide what you will make and what you will buy based on capability, control and cost.
    Rule of thumb
    If a part takes longer to get than to design, order it before the design is final, and accept that some of that money is at risk.
    Common pitfalls
    Discovering a 20-week lead time at pilot build; single-source parts with no qualified alternative; buying off-the-shelf parts without checking the supplier’s change policy.
    Evidence to show
    Make-or-buy decisions, critical components list, lead times and sourcing plan.
  6. Good practiceOperations

    People who will build and test the device catch problems with fixtures and processes while they are still drawings. See it go wrong in the case study below ↓

    Read more
    Good practice
    Choose the manufacturing site or contract manufacturer early enough that its engineers can review drawings, tolerances and test methods before design freeze.
    Rule of thumb
    The people who will build it should see the design while it can still change.
    Common pitfalls
    Selecting a contract manufacturer on price only; involving them after design freeze; no written agreement on responsibilities for validation and records.
    Evidence to show
    Supplier selection record, quality agreement and evidence of manufacturing input to design reviews.
  7. Added for your deviceGood practiceRegulatory

    Notified body queues can be longer than your design schedule.

    Read more
    Good practice
    Confirm the notified body is designated for your device codes, ask about current lead times, and agree the application and review timeline.
    Rule of thumb
    Contact notified bodies before design freeze, not when the file is ready.
    Common pitfalls
    Choosing a body whose designation doesn’t cover the device; discovering long queues after the file is finished.
    Evidence to show
    Notified body agreement, confirmation of scope and the agreed timeline.
  8. Added for your deviceRequiredRegulatoryEU MDR Art. 11, 15, 29(3), 31[3]

    The notified body needs your SRN and Basic UDI-DI to take the application and issue the certificate.

    Read more
    Good practice
    Complete actor registration, name the PRRC, sign the authorised representative mandate if you’re outside the EU, and assign Basic UDI-DIs before you apply.
    Rule of thumb
    Your SRN and Basic UDI-DI come before the application, not before the first shipment.
    Common pitfalls
    Applying before the SRN is issued; Basic UDI-DIs assigned inconsistently with how the technical documentation is grouped.
    Evidence to show
    SRN, PRRC designation, authorised representative mandate and the Basic UDI-DI list.
  9. Good practiceR&DQualityISO 13485 7.3.6, 7.3.7[1]

    Validation has to use product that represents production, so the build plan and the test plan must agree. See it go wrong in the case study below ↓

    Read more
    Good practice
    Plan which verification and validation activities run on which build, and why that build represents production. Include usability, software, biocompatibility, sterilization and clinical evidence where they apply.
    Rule of thumb
    Write down the build for each test now. If the answer is “whatever we have”, plan for repeats.
    Common pitfalls
    Running pivotal tests on engineering prototypes; no plan for changes between builds; validation scheduled before production processes exist.
    Evidence to show
    Verification and validation plan, with a build plan and rationale for each activity.
  10. Added for your deviceRequiredR&DClinicalISO 13485 7.3.3; EU MDR Annex I 17[1][3]

    Model performance is only as trustworthy as the data behind it, and reviewers ask how test data was kept independent.

    Read more
    Good practice
    Document where data comes from, how it is labeled and checked, how training, tuning and test sets are kept independent, and whether the test data represents the intended users and settings.
    Rule of thumb
    Lock the test set before development starts, and keep it away from the people tuning the model.
    Common pitfalls
    Test data drawn from the same sites or patients as training data; gaps in the populations the device will meet.
    Evidence to show
    Data management plan, dataset descriptions and independence records.
  11. Added for your deviceGood practiceRegulatoryRegulation (EU) 2024/1689[10]

    Regulation (EU) 2026/1744 postponed the high-risk obligations for AI in products covered by EU product legislation, including medical devices; confirm the application date that applies before planning.

    Read more
    Good practice
    Check whether the AI system falls under the AI Act’s high-risk category for regulated products, and plan how its requirements fit into your existing QMS and notified body assessment.
    Rule of thumb
    Plan for one combined technical file where you can, not two separate ones.
    Common pitfalls
    Treating AI Act work as separate from MDR or IVDR compliance; planning around dates that have since changed.
    Evidence to show
    AI Act applicability assessment and the integration plan.
  12. Added for your deviceRequiredRegulatoryClinical21 CFR Part 812[11]

    Nonsignificant-risk studies have abbreviated requirements; significant-risk studies need FDA approval first, including some that support a 510(k).

    Read more
    Good practice
    Decide whether the study is significant risk, and get IDE approval and institutional review board approval before enrolling.
    Rule of thumb
    If in doubt about significant risk, ask FDA early.
    Common pitfalls
    Starting enrollment before approvals; protocol changes without the required notifications.
    Evidence to show
    IDE approval letter, IRB approvals and study records.
  13. Added for your deviceRequiredClinicalRegulatoryEU MDR Art. 61–62[3]

    For Class III and implantable devices, clinical investigations are the default, with limited exceptions.

    Read more
    Good practice
    Plan the clinical investigation to answer the questions the clinical evaluation can’t, and check whether any exception for not doing one applies.
    Rule of thumb
    Start talking to the notified body about clinical evidence well before you submit.
    Common pitfalls
    Assuming equivalence to another manufacturer’s device without access to its technical documentation.
    Evidence to show
    Clinical evaluation plan, investigation plan or documented justification.
  14. Added for your deviceRequiredClinicalRegulatoryEU IVDR Art. 56–58, Annex XIII[12]

    IVDR expects clinical performance studies unless you can justify relying on other sources of clinical performance data.

    Read more
    Good practice
    Plan clinical performance studies where existing data can’t show clinical performance for the intended population and specimen types.
    Rule of thumb
    Match the study population to the claim you want to make.
    Common pitfalls
    Studies on populations or specimen types that don’t match the intended use.
    Evidence to show
    Performance evaluation plan and clinical performance study reports.
  15. Added for your deviceRequiredClinicalRegulatoryEU MDR Art. 61, Annex XIV Part A[3]

    Every EU class needs a clinical evaluation; a late plan usually means late evidence.

    Read more
    Good practice
    Write the plan before collecting data: which requirements need clinical evidence, the claimed benefits, outcome measures, acceptance criteria and whether equivalence is realistic.
    Rule of thumb
    If you plan to claim equivalence, check you can get the other device’s technical data first.
    Common pitfalls
    Plans written to match data already collected; equivalence claims without access to the other manufacturer’s documentation.
    Evidence to show
    Approved clinical (or performance) evaluation plan.
  16. RequiredQualityISO 13485 7.3.5[1]

    Record who took part, what was decided and the actions that came out of it.

    Read more
    Good practice
    Hold the review with the functions involved in this stage and specialists where needed, record who attended, what was decided and the actions, and close actions before the next review.
    Rule of thumb
    A review with no actions is either a very good design or a very quiet room.
    Common pitfalls
    Reviews that are only status meetings; actions that never close; the same people reviewing their own work every time.
    Evidence to show
    Design review record with attendees, decisions, actions and their closure.

Gate 3

Design freeze

Is the design complete enough to verify, and is everything that could change it under control?

0 of 11
  1. RequiredR&DISO 13485 7.3.4, 4.2.4[1]

    Verification only counts if it was done on a known, controlled revision.

    Read more
    Good practice
    Release design outputs under document control with clear revision levels, and make sure manufacturing, suppliers and test labs work from released revisions only.
    Rule of thumb
    If it isn’t released, it doesn’t exist for verification.
    Common pitfalls
    Testing on drawings that are still in someone’s inbox; software builds without a recorded version; labeling drafts never placed under control.
    Evidence to show
    Released outputs list, with revisions and approval records.
  2. RequiredR&DISO 13485 7.3.4[1]

    Tracing now shows gaps before verification, not after.

    Read more
    Good practice
    Trace every design output to the input it satisfies, and every input to at least one output, with acceptance criteria that verification will use.
    Rule of thumb
    Gaps in the trace now are cheap. Gaps found during verification are expensive. Gaps found by an auditor are worse.
    Common pitfalls
    Trace matrices built at the end to fill a submission; acceptance criteria missing or vaguer than the requirement.
    Evidence to show
    Trace matrix from needs and inputs to outputs and planned verification.
  3. Added for your deviceRequiredR&DIEC 62304; FD&C Act section 524B; EU MDR Annex I 17[8][9][3]

    For cyber devices, the threat model and software bill of materials are expected in the US submission, so they can’t wait for launch.

    Read more
    Good practice
    List every third-party component with its version, requirements and known anomalies, model the threats to the system, and keep the software bill of materials in sync with the build.
    Rule of thumb
    If a library is in the build, it belongs in the software bill of materials.
    Common pitfalls
    Open-source components pulled in without review; threat models done after the design is fixed; an SBOM that doesn’t match the release.
    Evidence to show
    SOUP list with anomaly evaluation, threat model, security architecture and SBOM.
  4. RequiredR&DQualityISO 14971 clauses 5, 7[7]

    Each risk control needs evidence that it is implemented and effective.

    Read more
    Good practice
    Analyse how design failures could lead to hazardous situations, link each risk control to a requirement and a planned verification, and update the analysis as the design changes.
    Rule of thumb
    Every risk control needs two pieces of evidence: that it is implemented, and that it works.
    Common pitfalls
    FMEAs scored to make risks look acceptable; controls that rely only on warnings when design changes were possible; analysis frozen while the design keeps moving.
    Evidence to show
    Design risk analysis, risk control trace and planned verification of effectiveness.
  5. RequiredR&DIEC 62366-1[6]

    A surprise in summative testing is the most expensive place to find a user interface problem.

    Read more
    Good practice
    Run several small formative studies as the user interface develops, with representative users, and record what changed as a result.
    Rule of thumb
    Test early with rough prototypes. Users find problems in paper mock-ups too.
    Common pitfalls
    Skipping formative work to save time; formative studies only with internal staff; findings logged but not acted on.
    Evidence to show
    User interface specification and formative evaluation records with design changes.
  6. Added for your deviceRequiredR&DRegulatoryEU MDR Annex I 22; IEC 60601-1-11[3][13]

    Lay users read less, misread more and use devices in uncontrolled settings.

    Read more
    Good practice
    Design for people without training, in homes with children, pets, poor lighting and interruptions, and write instructions tested with real lay users.
    Rule of thumb
    Assume lay users will skip the instructions, and design so the device is still safe.
    Common pitfalls
    Instructions written by engineers; reading level too high; no testing in a home-like setting.
    Evidence to show
    Use specification for lay users, labeling comprehension or usability results, and home-use test reports.
  7. Good practiceR&DOperationsISO 11607-1[14]

    Sterilization validation, packaging validation and shelf-life aging all depend on the final package. See it go wrong in the case study below ↓

    Read more
    Good practice
    Freeze the sterile barrier system and packaging before starting sterilization validation, packaging validation and aging, because each depends on the final configuration.
    Rule of thumb
    Packaging is on the critical path, even when nobody puts it there.
    Common pitfalls
    Changing pouch size or material after validation starts; choosing packaging without checking compatibility with the sterilization method; forgetting the shipping configuration.
    Evidence to show
    Released packaging specifications and the packaging validation plan.
  8. Good practiceQuality

    A small open item can quietly restart sterilization, packaging or aging work. See it go wrong in the case study below ↓

    Read more
    Good practice
    Track each gate condition as an action with an owner and a due date, and check what it could affect downstream, such as validations, tooling or submissions.
    Rule of thumb
    Ask of every open item: if this changes, what would we have to redo?
    Common pitfalls
    Conditions recorded only in meeting minutes; “minor” items that restart validations; conditions quietly rolled forward gate after gate.
    Evidence to show
    Gate conditions log with owners, dates, impact checks and closure evidence.
  9. RequiredR&DQualityISO 13485 7.3.9[1]

    Design change control applies before launch too; many repeated tests come from changes nobody assessed.

    Read more
    Good practice
    After freeze, route every change through a change request that assesses impact on verification, validation, risk, labeling, suppliers and submissions before approval.
    Rule of thumb
    After freeze, there are no small changes, only assessed ones.
    Common pitfalls
    Changes made directly to drawings; impact on completed testing not assessed; submissions not updated.
    Evidence to show
    Change records with impact assessments and approvals.
  10. RequiredOperationsQualityISO 13485 4.1.5, 7.4.1, 7.4.2[1]

    A supplier change you hear about after the fact can cost weeks of investigation and requalification. See it go wrong in the case study below ↓

    Read more
    Good practice
    Rank suppliers by how much their part affects safety and performance, set controls to match, and put written agreements in place, including notice before changes.
    Rule of thumb
    Your critical suppliers are part of your design. Control them like it.
    Common pitfalls
    Agreements signed after the first problem; no change notification clause; distributors standing between you and the real manufacturer.
    Evidence to show
    Supplier evaluations, approved supplier list, quality agreements and purchasing specifications.
  11. Good practiceR&DISO 13485 7.3.6, 7.3.7[1]

    Testing on hand-built units can mean repeating it on production units. See it go wrong in the case study below ↓

    Read more
    Good practice
    Use units built with production materials, processes and tooling for verification where possible, and document any differences and why they don’t affect the results.
    Rule of thumb
    If a difference could plausibly change a result, assume it does until you show it doesn’t.
    Common pitfalls
    Hand-built units with tighter tolerances than production; prototype materials swapped later; no record of which build was tested.
    Evidence to show
    Build records for verification units and a justification for any differences from production.
  12. RequiredQualityISO 10993-1[15]

    Material, process and sterilization choices all feed the evaluation.

    Read more
    Good practice
    Start the biological evaluation from the materials, processing and patient contact, and use existing data and chemical characterization before planning animal or lab tests.
    Rule of thumb
    Plan the evaluation as soon as materials are chosen. A material change late in development can restart it.
    Common pitfalls
    Testing raw materials instead of the finished, processed device; forgetting colorants, adhesives or processing aids; ignoring the effect of sterilization.
    Evidence to show
    Biological evaluation plan with material characterization and the testing strategy.
  13. RequiredQualityISO 13485 7.3.5[1]

    Record the decision, the open items and who accepted them.

    Read more
    Good practice
    Review the frozen design against the inputs, the risk analysis and the verification plan, and record any open items accepted as conditions.
    Rule of thumb
    Freeze means changes now go through formal change control, not a hallway conversation.
    Common pitfalls
    Declaring freeze while key outputs are still changing; no change control between freeze and transfer.
    Evidence to show
    Design review record and the baseline of released outputs.

Gate 4

Verification and validation complete

Have we proven the design meets its requirements and its users’ needs?

0 of 11
  1. RequiredR&DISO 13485 7.3.6[1]

    Every input needs a verification result, or a documented reason why it is covered another way.

    Read more
    Good practice
    Verify each input with a method that is suitable and validated where needed, record results and conclusions, and investigate every failure before retesting.
    Rule of thumb
    A retest without an investigation is a coin toss, not verification.
    Common pitfalls
    Sample sizes with no rationale; test methods that weren’t validated; failures explained away; verification on an unreleased revision.
    Evidence to show
    Verification protocols and reports, traced to inputs, with sample size rationale and deviations.
  2. RequiredR&DClinicalISO 13485 7.3.7; EU MDR Art. 61[1][3]

    Validation shows the device meets user needs and intended uses, not just its specifications. See it go wrong in the case study below ↓

    Read more
    Good practice
    Validate on product that represents production, under real or simulated use conditions, with representative users, and record why the units used are representative.
    Rule of thumb
    Verification proves the design meets its inputs. Validation proves the device meets the user’s needs. You need evidence for both.
    Common pitfalls
    Validating on prototypes; validating only in ideal conditions; clinical evidence that doesn’t cover the full intended use.
    Evidence to show
    Validation plan and report, clinical evaluation or performance evaluation, and the rationale for the units used.
  3. Added for your deviceRequiredR&DISO 13485 7.3.6; EU IVDR Annex XIII[1][12]

    Studies often follow CLSI methods and should use product made by the production process.

    Read more
    Good practice
    Run analytical studies on product made by the production process, using recognized protocols, and report results against predefined acceptance criteria.
    Rule of thumb
    Define acceptance criteria before you run the study, not after you see the data.
    Common pitfalls
    Studies on development lots only; interferents chosen without considering the intended population.
    Evidence to show
    Analytical performance study protocols and reports.
  4. RequiredR&DIEC 62366-1[6]

    Representative users, realistic conditions and production-equivalent devices.

    Read more
    Good practice
    Test the critical tasks with representative users, realistic environments and production-equivalent devices, including labeling and training as delivered.
    Rule of thumb
    If the summative test finds a new use error, analyse its root cause and risk; if the risk isn’t acceptable, go back to design.
    Common pitfalls
    Using employees or expert users as participants; testing only the happy path; training participants more than real users will be trained.
    Evidence to show
    Use-related risk analysis, human factors validation protocol and report, with root cause analysis of observed use errors.
  5. Added for your deviceRequiredR&DRegulatoryFDA MR environment guidance; ASTM F2503; EU MDR Annex I 23.4, Art. 18[16][17][3]

    Patients with implants get MRI scans; missing MR labeling is a common reviewer question.

    Read more
    Good practice
    Test magnetically induced displacement and torque, RF heating and image artifacts as relevant, and label the MR conditions clearly on the device labeling and implant card.
    Rule of thumb
    If the device goes into the body, assume it will meet an MRI scanner.
    Common pitfalls
    Testing only one field strength; MR conditions missing from the implant card.
    Evidence to show
    MR safety test reports and MR labeling.
  6. Added for your deviceRequiredR&DGeneral safety and performance requirements; IEC 60601 series[18]

    Test labs book up early, and a failed EMC test can mean a board respin.

    Read more
    Good practice
    Book test labs early, test pre-compliance first, and plan for at least one round of fixes.
    Rule of thumb
    Assume your first EMC test will find something.
    Common pitfalls
    Testing late with no time to redesign; testing a configuration different from the production one.
    Evidence to show
    Electrical safety and EMC test reports for the production configuration.
  7. Added for your deviceRequiredR&DOperationsDirective 2011/65/EU; Directive 2012/19/EU; Regulation (EU) 2023/1542; 49 CFR 173.185[19][20][21][22]

    Carriers won’t ship lithium batteries without a UN 38.3 test summary.

    Read more
    Good practice
    Check material restrictions, take-back and battery labeling early, and get the UN 38.3 test summary from the battery supplier before the first shipment.
    Rule of thumb
    Ask for the UN 38.3 test summary when you choose the battery, not when you book freight.
    Common pitfalls
    Batteries changed late without new test summaries; WEEE marking missing from labels.
    Evidence to show
    RoHS documentation, WEEE marking, battery labeling and UN 38.3 test summary.
  8. Added for your deviceRequiredR&DRegulatoryDirective 2014/53/EU; 47 CFR Part 2, Subpart J; FDA wireless guidance[23][24][25]

    In the US, a radio device generally can’t be marketed before its FCC authorization.

    Read more
    Good practice
    Plan radio approvals early, test wireless coexistence in realistic environments, and keep the radio configuration fixed once tested.
    Rule of thumb
    Changing the antenna or firmware radio settings can mean retesting.
    Common pitfalls
    Using a pre-certified module but changing its antenna or enclosure; coexistence tested only on a bench.
    Evidence to show
    Radio test reports, equipment authorization and coexistence test results.
  9. RequiredR&DIEC 62304; FD&C Act section 524B[8][9]

    Release the exact software build that was verified.

    Read more
    Good practice
    Verify software against its requirements and risk controls at unit, integration and system level as the safety class requires, and include cybersecurity testing such as penetration testing where applicable.
    Rule of thumb
    The build in the release record should be the same build that’s in the test report.
    Common pitfalls
    Last-minute fixes after verification; third-party software not assessed; known anomalies not evaluated for risk.
    Evidence to show
    Software verification records, anomaly list with risk evaluation, and cybersecurity test reports.
  10. Added for your deviceGood practiceR&DIEC 82304-1[26]

    IEC 82304-1 covers the product as a whole, around the IEC 62304 software life cycle.

    Read more
    Good practice
    Cover the product-level requirements around the software, such as installation, documentation, security and decommissioning.
    Rule of thumb
    Think about how the software is installed, updated and retired, not just how it is built.
    Common pitfalls
    Focusing only on code and forgetting accompanying documents and deployment.
    Evidence to show
    Product requirements and validation records against IEC 82304-1.
  11. RequiredQualityISO 10993-1[15]

    Testing on the final, sterilized device, or a justification for using existing data.

    Read more
    Good practice
    Complete the biological evaluation on the final, sterilized device, combining existing data, chemical characterization and testing, and conclude on biological safety in a report.
    Rule of thumb
    The device that went through the evaluation should be the device you ship.
    Common pitfalls
    Testing an earlier material or process; skipping cumulative-contact considerations for repeat-use devices; a test-only approach with no risk assessment.
    Evidence to show
    Biological evaluation report with the data and rationale behind each conclusion.
  12. Added for your deviceRequiredR&DRegulatoryEU MDR Annex I 10.4; REACH Art. 33[3][27]

    Phthalates and similar substances can force late design or labeling changes.

    Read more
    Good practice
    Screen materials and components early, ask suppliers for substance declarations, and justify and label any restricted substances you can’t avoid.
    Rule of thumb
    Ask suppliers for substance declarations at selection, not after the first audit finding.
    Common pitfalls
    Relying on supplier statements without data; colorants and adhesives missed.
    Evidence to show
    Material screening, supplier declarations and any justification and labeling.
  13. RequiredOperationsQualityISO 13485 7.5.7; ISO 11135, ISO 11137 or ISO 17665 by method; ISO 11737-1; ISO 10993-7 for ethylene oxide[1][28][29][30][31][32]

    For ethylene oxide, residual results can extend aeration and push the schedule. See it go wrong in the case study below ↓

    Read more
    Good practice
    Validate the sterilization process for the final product and load configuration, and confirm residuals are within limits after the planned aeration.
    Rule of thumb
    Sterilization validation is only as good as the product and load it was run on.
    Common pitfalls
    Changing load density or packaging after validation; residual testing on the wrong samples; no plan for routine monitoring and revalidation.
    Evidence to show
    Sterilization validation report, residual test results and routine control plan.
  14. RequiredR&DOperationsISO 11607-1; ASTM F1980[14][33]

    The expiry date you can claim at launch shapes how much stock to build. See it go wrong in the case study below ↓

    Read more
    Good practice
    Validate the packaging system, including transport testing, and start aging on final product as early as possible. Agree the launch expiry date with commercial and supply chain teams.
    Rule of thumb
    Your launch expiry date is set by when aging started, not by when you need it.
    Common pitfalls
    Aging started late on the wrong configuration; accelerated aging run at temperatures that damage materials; real-time aging never followed up.
    Evidence to show
    Packaging validation report, aging protocols and the expiry date justification.
  15. Added for your deviceRequiredR&DQualityFDA reprocessing guidance; ISO 17664-1[34][35]

    Instructions that can’t be followed in a real hospital department will fail in the field.

    Read more
    Good practice
    Validate cleaning and disinfection or sterilization instructions with realistic soiling, and write them so a hospital department can follow them.
    Rule of thumb
    If the instructions need equipment the user doesn’t have, they will be ignored.
    Common pitfalls
    Validating with clean devices; instructions that differ from what was validated.
    Evidence to show
    Reprocessing validation reports and the instructions for use.
  16. Added for your deviceRequiredR&DOperationsISO 13485 7.5.11; EU IVDR Annex II[1][12]

    Real-time stability takes as long as the claim, so start it on the first validation lots.

    Read more
    Good practice
    Start real-time stability on validation lots as early as possible, and support claims for shelf life, in-use and shipping conditions with data.
    Rule of thumb
    A shelf-life claim can’t be longer than the data behind it, except where a justified accelerated approach is used.
    Common pitfalls
    Shipping stability forgotten; in-use claims based on assumptions.
    Evidence to show
    Stability protocols, data and the justification for each claim.
  17. RequiredQualityISO 14971 clauses 7–8[7]

    Verification results can change risk estimates; update them before release.

    Read more
    Good practice
    Update risk estimates with verification and validation results, evaluate overall residual risk, and document the benefit-risk conclusion before release.
    Rule of thumb
    Test results are new information. If they didn’t change anything in the risk file, check again.
    Common pitfalls
    Risk file updated only at the end, without the evidence trail; residual risks not disclosed in labeling where they should be.
    Evidence to show
    Updated risk management file with evaluation of residual risk and benefit-risk.
  18. Added for your deviceRequiredRegulatoryEU MDR Art. 10, 61, Annexes II–III[3]

    The notified body reviews this file, and self-certified devices need it too.

    Read more
    Good practice
    Build the technical documentation as you go, organised by the annex headings, with the GSPR checklist pointing to the evidence for each requirement.
    Rule of thumb
    If the GSPR checklist says “see test report”, name the report and its revision.
    Common pitfalls
    Files assembled at the end; GSPR entries that don’t point to real evidence; clinical evaluation report out of date with the final design.
    Evidence to show
    Technical documentation, GSPR checklist and approved clinical or performance evaluation report.
  19. RequiredRegulatoryR&D21 CFR Part 801; ISO 15223-1; EU MDR Annex I 23, Art. 10(11); Regulation (EU) 2021/2226[36][37][3][38]

    Labeling controls check printing; this check is about the content, and translations take longer than teams expect.

    Read more
    Good practice
    Check label and IFU content against each market’s rules, use standard symbols with an explanation, plan translations early, and confirm whether electronic instructions are allowed for your device and users.
    Rule of thumb
    Start translations as soon as the IFU text is stable; they always take longer than planned.
    Common pitfalls
    Symbols used without a glossary; translations not reviewed by native speakers with product knowledge; electronic instructions offered where paper is required.
    Evidence to show
    Labeling content review record, translations and their verification.
  20. Good practiceRegulatory

    Sterilization, biocompatibility, software and cybersecurity sections are common sources of questions. See it go wrong in the case study below ↓

    Read more
    Good practice
    Have someone who wasn’t on the project read the submission as a reviewer would, focusing on the areas that most often draw questions.
    Rule of thumb
    If a reviewer has to search for your answer, assume they will ask for it.
    Common pitfalls
    Inconsistent device descriptions across sections; test reports that don’t match the claims; missing rationale for test choices.
    Evidence to show
    Internal submission review record and the final submission package.
  21. Added for your deviceRequiredRegulatoryFDA eSTAR program; MDUFA user fees[39][40]

    An unpaid fee or an incomplete eSTAR stops the review before it starts.

    Read more
    Good practice
    Use the current eSTAR template, pay the user fee before sending, and apply for a small business determination early if you qualify.
    Rule of thumb
    Check the fee is paid before you submit, not after.
    Common pitfalls
    Outdated templates; missing attachments that eSTAR flags; small business status requested too late to use.
    Evidence to show
    eSTAR submission, payment confirmation and any small business determination.
  22. Added for your deviceGood practiceRegulatoryR&DFD&C Act section 515C; FDA PCCP guidance[41]

    Changes described in an authorized plan can be made without a new submission.

    Read more
    Good practice
    Describe the planned modifications, how they’ll be developed and validated, and how their impact will be assessed, and include the plan in the marketing submission.
    Rule of thumb
    Only planned changes described in an authorized plan are covered.
    Common pitfalls
    Plans too vague to authorize; changes made that weren’t in the plan.
    Evidence to show
    Predetermined change control plan in the submission and the authorization.
  23. Added for your deviceRequiredRegulatoryClinicalEU IVDR Art. 29[12]

    Required for Class C and D devices.

    Read more
    Good practice
    Prepare the summary of safety and performance consistent with the technical documentation, in language suited to its readers.
    Rule of thumb
    Draft it alongside the performance evaluation, not after.
    Common pitfalls
    Summaries inconsistent with the performance evaluation report.
    Evidence to show
    Summary of safety and performance submitted to the notified body.
  24. Added for your deviceRequiredRegulatoryClinicalEU MDR Art. 32[3]

    Required for implantable and Class III devices; it goes to the notified body with the technical documentation and is published in EUDAMED.

    Read more
    Good practice
    Write the summary for its intended readers, including patients where relevant, and keep it consistent with the technical documentation.
    Rule of thumb
    If it contradicts the instructions for use, the notified body will catch it.
    Common pitfalls
    Summaries written in technical language for patients.
    Evidence to show
    Validated summary of safety and clinical performance.
  25. Added for your deviceGood practiceRegulatoryEU IVDR Art. 9, 48, 100[12]

    Reference laboratory verification adds time to the notified body review.

    Read more
    Good practice
    Plan the reference laboratory and common specification steps into the timeline for Class D devices.
    Rule of thumb
    Add time for reference laboratory verification to your EU launch plan.
    Common pitfalls
    Leaving reference laboratory steps out of the schedule.
    Evidence to show
    Plan for reference laboratory involvement and common specification compliance.
  26. RequiredQualityISO 13485 7.3.5[1]

    Confirm every input is verified and every user need validated.

    Read more
    Good practice
    Confirm every input has verification evidence, every user need has validation evidence, and the risk file reflects the results.
    Rule of thumb
    If any trace line ends without evidence, the gate isn’t ready.
    Common pitfalls
    Signing off with open test failures; validation pending “after launch”.
    Evidence to show
    Design review record with the trace and evidence summary.

Gate 5

Transfer and production readiness

Can we build, test and release this device consistently, every time?

0 of 14
  1. RequiredOperationsR&DISO 13485 7.3.8[1]

    Transfer is a thread through development, not a single handoff at the end. See it go wrong in the case study below ↓

    Read more
    Good practice
    Check that each specification can be built and measured on the production line, with the tolerances, fixtures and skills available there, before releasing it for production.
    Rule of thumb
    Transfer is a series of small handovers, not one big one at the end.
    Common pitfalls
    Tolerances only the engineering lab can hold; specifications that assume tools the line doesn’t have; manufacturing seeing drawings for the first time at transfer.
    Evidence to show
    Manufacturability reviews, transfer plan and release records.
  2. RequiredQualityISO 13485 4.2.3[1]

    This is what the old FDA rules called the device master record.

    Read more
    Good practice
    Build the medical device file as items are released, with references to controlled documents rather than copies, and assign an owner to keep it current.
    Rule of thumb
    If it takes more than a few minutes to find a current specification, the file isn’t working.
    Common pitfalls
    Files assembled the week before launch; copies that drift from the controlled originals; servicing and installation forgotten.
    Evidence to show
    Medical device file index with links to controlled documents.
  3. RequiredOperationsISO 13485 7.5.6; GHTF SG3/N99-10[1][42]

    Bonding, sealing, molding and sterilization usually need validation, not just inspection.

    Read more
    Good practice
    Decide for each process whether its output can be fully verified afterwards. Where it can’t, validate it with installation, operational and performance qualification, and define revalidation triggers.
    Rule of thumb
    If you can’t check every unit without destroying it, validate the process.
    Common pitfalls
    Treating inspection as a substitute for validation of sealing, bonding or molding; validating at one set of parameters, then running at others; no revalidation after changes.
    Evidence to show
    Process validation protocols and reports, with parameter windows and revalidation criteria.
  4. RequiredQualityOperationsISO 13485 4.1.6, 7.5.6, 7.6[1]

    Test-station and label-printing software is often missed in process validation.

    Read more
    Good practice
    List software used in production, testing, labeling and the QMS, and validate each for its intended use, scaled to risk.
    Rule of thumb
    If software makes or records a quality decision, it needs validation.
    Common pitfalls
    Test-station scripts and label templates never validated; spreadsheets used as records without control.
    Evidence to show
    Software inventory and validation records.
  5. Good practiceOperationsQualityISO 13485 7.6[1]

    A method that only works in the engineering lab isn’t ready for the line. See it go wrong in the case study below ↓

    Read more
    Good practice
    Validate test and inspection methods on production fixtures, with the operators who will use them, using gauge or measurement system studies where appropriate.
    Rule of thumb
    A test method is part of the product. If it can’t tell good from bad reliably, neither can you.
    Common pitfalls
    Methods developed by one engineer and never transferred; fixtures changed after the study; visual inspection with no defined criteria or training.
    Evidence to show
    Test method validation or gauge study reports and approved inspection procedures.
  6. RequiredOperationsISO 14971; ISO 13485 8.2.6[7][1]

    Each process risk control should show up as a check on the line.

    Read more
    Good practice
    Analyse how manufacturing steps could lead to hazards, and make sure each process risk control shows up as a check, limit or validated parameter on the line.
    Rule of thumb
    Every process risk control should be visible to an operator.
    Common pitfalls
    Process risk analysis done once and never updated; controls listed in the analysis but missing from work instructions.
    Evidence to show
    Process risk analysis linked to work instructions, inspection points and validated parameters.
  7. RequiredQualityOperationsISO 13485 7.4.2, 7.4.3[1]

    Choosing good suppliers doesn’t check what they deliver.

    Read more
    Good practice
    Define what is checked on receipt for each purchased part, how much, and when you can reduce checks based on supplier performance.
    Rule of thumb
    Reduce inspection only after the supplier has earned it with data.
    Common pitfalls
    No incoming checks for critical parts; certificates accepted without verification.
    Evidence to show
    Incoming inspection procedures, purchasing specifications and inspection records.
  8. RequiredOperationsISO 13485 6.3, 7.6[1]

    Calibration status should be visible to the people using the equipment.

    Read more
    Good practice
    Qualify production equipment, calibrate measuring equipment against traceable standards, and schedule maintenance, with status visible on the equipment.
    Rule of thumb
    If an operator can’t tell whether a gauge is in calibration, assume it isn’t.
    Common pitfalls
    Equipment used before qualification; calibration intervals copied without rationale; no plan for out-of-tolerance findings.
    Evidence to show
    Equipment qualification records, calibration records and maintenance schedules.
  9. RequiredOperationsISO 13485 6.4; ISO 14644-1; ISO 11737-1[1][43][31]

    Sterilization validation assumes the bioburden stays under control.

    Read more
    Good practice
    Define and qualify the environment the product needs, monitor it, and connect results to bioburden and product quality.
    Rule of thumb
    Sterilization validation assumes your bioburden. Monitor it so the assumption stays true.
    Common pitfalls
    Cleanroom classified once and never monitored; bioburden not tracked over time.
    Evidence to show
    Environment specification, qualification and monitoring records, and bioburden data.
  10. Added for your deviceGood practiceQualityOperations

    FDA generally inspects manufacturing before approving a PMA.

    Read more
    Good practice
    Prepare manufacturing sites for a pre-approval inspection, with validation, training and records ready for review.
    Rule of thumb
    Run a mock inspection with someone who wasn’t involved in setting up the line.
    Common pitfalls
    Records incomplete because the line was still being set up during review.
    Evidence to show
    Mock inspection report and actions.
  11. RequiredOperationsQualityISO 13485 6.2[1]

    Train on released procedures, not drafts.

    Read more
    Good practice
    Train production staff on released procedures, check their competence, and keep records that show who can perform each task.
    Rule of thumb
    Train on the procedure you’ll use, not the draft you had.
    Common pitfalls
    Training on drafts that later change; competence never assessed; temporary staff missing from the records.
    Evidence to show
    Training records and competence assessments matched to procedures and roles.
  12. RequiredOperationsQuality21 CFR 820.45[44]

    Checks cover the UDI, expiration date, storage and handling instructions.

    Read more
    Good practice
    Inspect labeling for accuracy before release, including the UDI, expiry date and storage instructions, separate different labels physically, and record who released them and when.
    Rule of thumb
    Labeling mix-ups often happen at changeovers. Control the line clearance.
    Common pitfalls
    Old labels left on the line; label artwork approved without checking printed output; no reconciliation of issued and used labels.
    Evidence to show
    Labeling inspection and release records, line clearance records and approved artwork.
  13. Added for your deviceRequiredRegulatory21 CFR 809.10[45]

    IVD labeling has its own content requirements on top of the general labeling rules.

    Read more
    Good practice
    Check labeling against each element required for IVDs, including intended use, limitations and performance characteristics.
    Rule of thumb
    Build a checklist from the regulation and tick every element before release.
    Common pitfalls
    Performance claims that don’t match study results.
    Evidence to show
    Labeling review record against the requirements.
  14. RequiredRegulatoryOperations21 CFR 801.20, Part 830; EU MDR Art. 27–29[46][3]

    UDI data is needed before labels can be printed and before devices can be registered. See it go wrong in the case study below ↓

    Read more
    Good practice
    Assign device identifiers for each model and packaging level, prepare the database records, and check the barcodes print and scan correctly on final packaging.
    Rule of thumb
    Do the UDI data before label artwork is final, not after.
    Common pitfalls
    Data mismatches between labels and the database; packaging levels missed; a new identifier forgotten after a change that requires one.
    Evidence to show
    UDI assignment records, database submissions and label verification.
  15. RequiredQualityISO 13485 7.5.1; 21 CFR 820.35(c)[1][44]

    This replaces what the old FDA rules called the device history record.

    Read more
    Good practice
    Define what the record for each device or batch contains, including quantities, dates, acceptance results, the UDI and any deviations, and make it easy to retrieve.
    Rule of thumb
    If a complaint arrives, you should be able to pull the full build history within the hour.
    Common pitfalls
    Records scattered across paper and systems; deviations not linked; missing link between a shipped unit and its components.
    Evidence to show
    Record template and a completed example from a pilot or validation lot.
  16. Added for your deviceRequiredQualityISO 13485 7.5.9.2[1]

    Implant traceability has to reach the components and the consignee of each device.

    Read more
    Good practice
    Record components, materials and the consignee for each implantable device, so you can trace both ways quickly.
    Rule of thumb
    Test your traceability with a mock recall before launch.
    Common pitfalls
    Distribution records that stop at the distributor.
    Evidence to show
    Traceability records and a mock recall result.
  17. Added for your deviceRequiredR&DQualityIEC 62304 clause 5.8[8]

    You should be able to rebuild exactly what you released.

    Read more
    Good practice
    Define how a release is built, versioned, documented and approved, so you can rebuild exactly what you shipped.
    Rule of thumb
    If you can’t rebuild last month’s release, your configuration management isn’t working.
    Common pitfalls
    Releases built on a developer’s machine; release notes missing known anomalies.
    Evidence to show
    Release procedure and release records.
  18. Good practiceOperations

    The first lots expose tooling, fixture and supplier problems before customers see them. See it go wrong in the case study below ↓

    Read more
    Good practice
    Build pilot or validation lots on the production line with production staff and materials, inspect first articles against drawings, and feed findings into fixes before launch.
    Rule of thumb
    The first lots are for learning. Plan time to act on what they teach you.
    Common pitfalls
    Pilot builds run by engineers instead of operators; first article results not reviewed; problems logged but not fixed before launch.
    Evidence to show
    Pilot lot records, first article inspection reports and the list of issues and their resolution.
  19. Added for your deviceRequiredRegulatoryOperationsFD&C Act sections 801(e), 802[47]

    Shipping uncleared devices from the US to the EU needs a specific export route.

    Read more
    Good practice
    Confirm the legal route for exporting devices that aren’t yet cleared in the US, and keep the required records.
    Rule of thumb
    Check the export route before the first EU shipment leaves a US site.
    Common pitfalls
    Shipping uncleared devices without checking the export requirements.
    Evidence to show
    Export route documentation and records.
  20. Added for your deviceRequiredOperationsQualityISO 13485 8.2.6[1]

    Reagent variability between lots is a common source of early complaints.

    Read more
    Good practice
    Define lot release tests and show consistency across several validation lots, including different reagent lots where relevant.
    Rule of thumb
    Use more than one lot of critical raw materials in validation.
    Common pitfalls
    Validation lots made from a single lot of each raw material.
    Evidence to show
    Lot release specifications and lot-to-lot study results.

Gate 6

Launch readiness

Can we legally ship, and are we ready for what happens after we do?

0 of 16
  1. RequiredRegulatoryFD&C Act section 510(k); EU MDR Art. 19–20[2][3]

    Inventory can be built before US clearance, but not sold, shipped commercially or taken orders for. See it go wrong in the case study below ↓

    Read more
    Good practice
    Confirm the marketing authorization covers exactly the device, configuration and claims you are launching in each market, before the first commercial shipment.
    Rule of thumb
    Ship what was cleared or certified, not what the team improved afterwards.
    Common pitfalls
    Changes made after submission without assessing whether they need a new submission; shipping to a market before the certificate is issued.
    Evidence to show
    Clearance letter, approval or certificate, EU declaration of conformity, and a configuration check against them.
  2. RequiredRegulatory21 CFR Part 807[2]

    Registration and listing are separate from clearance and easy to forget.

    Read more
    Good practice
    Register the establishment and list the device with FDA when required, and check that every site involved, including contract manufacturers and sterilizers, is registered where it needs to be.
    Rule of thumb
    Clearance doesn’t register you. Registration is a separate step.
    Common pitfalls
    Forgetting contract sites; listings not updated after changes; missing the annual renewal.
    Evidence to show
    Registration and listing confirmations.
  3. RequiredRegulatoryEU MDR Art. 29, 31; EUDAMED mandatory since 28 May 2026[3][48]

    New devices have no transition period. See it go wrong in the case study below ↓

    Read more
    Good practice
    Register the actor and the device in EUDAMED, with the Basic UDI-DI and UDI-DI data, before the first unit is placed on the EU market, and keep the data current after changes.
    Rule of thumb
    Since 28 May 2026, no registration means no first shipment of a new device in the EU.
    Common pitfalls
    Assuming the old voluntary rules; data that doesn’t match the labels or the technical documentation.
    Evidence to show
    EUDAMED actor and device registration records.
  4. RequiredRegulatoryEU MDR Art. 11, 15; 21 CFR 807.40[3][2]

    Micro and small enterprises may have the PRRC permanently available externally rather than on staff.

    Read more
    Good practice
    Designate the person responsible for regulatory compliance with the required expertise, and appoint authorised representatives and agents where the manufacturer is outside the market.
    Rule of thumb
    Name a deputy too. Regulatory responsibilities don’t pause for holidays.
    Common pitfalls
    Naming someone without the required qualifications; agreements with representatives that don’t cover their legal duties.
    Evidence to show
    Designation records, qualification evidence and representative agreements.
  5. RequiredQualityCommercialISO 13485 8.2.2; 21 CFR 820.35(a)[1][44]

    Calls treated as tech support are still complaints. See it go wrong in the case study below ↓

    Read more
    Good practice
    Define what counts as a complaint, make the route for logging one easy for everyone who talks to customers, and cover every component, accessory and software release.
    Rule of thumb
    Any report that a released device fell short is a complaint until you’ve decided otherwise. When in doubt, log it and close it with a reason.
    Common pitfalls
    Service calls and sales conversations that never reach the complaint system; procedures written only for the main component; no link to reportability decisions.
    Evidence to show
    Complaint procedure, training records for customer-facing staff and the complaint log.
  6. Added for your deviceRequiredRegulatoryCommercialEU MDR Art. 13, 14, 25[3]

    These operators share your obligations but won’t meet them unless the agreements spell them out.

    Read more
    Good practice
    Agree in writing what importers and distributors must do: check CE marking and labeling, add importer details, forward complaints, keep storage conditions and records.
    Rule of thumb
    Your importer is your first line of EU compliance. Brief them like it.
    Common pitfalls
    Importer details missing from packaging; complaints stuck at distributors.
    Evidence to show
    Importer and distributor agreements and their EUDAMED registrations.
  7. Added for your deviceRequiredCommercialEU MDR Art. 10(16)[3]

    The new EU Product Liability Directive also covers software, for products placed on the market or put into service after 9 December 2026.

    Read more
    Good practice
    Arrange product liability cover proportionate to the device’s risk and your company size, and check how new rules covering software affect it.
    Rule of thumb
    Check the cover includes software and AI features, not just hardware.
    Common pitfalls
    Policies that exclude software or the EU.
    Evidence to show
    Insurance certificate or equivalent financial coverage.
  8. RequiredQualityRegulatory21 CFR 803.17; EU MDR Art. 87–88[49][3]

    Deadlines start when you become aware of an event, not when the investigation ends.

    Read more
    Good practice
    Write procedures that identify, evaluate and report events within the required timelines in each market, and practise them before launch.
    Rule of thumb
    The reporting clock starts when the company becomes aware, which is usually earlier than when the report reaches quality.
    Common pitfalls
    Treating “still investigating” as a reason to wait; unclear criteria for what is reportable; no one trained to submit reports.
    Evidence to show
    Reporting procedures, decision criteria and training records.
  9. RequiredQualityEU MDR Art. 84; ISO 13485 8.2.1[3][1]

    Define what “higher than expected” means before the data arrives.

    Read more
    Good practice
    Plan which data you will collect after launch, how often you will analyse it, and the thresholds that trigger action, and connect it to the risk file.
    Rule of thumb
    Define “higher than expected” before the data arrives.
    Common pitfalls
    Plans that list sources but no analysis; thresholds missing; field data never fed back to risk management.
    Evidence to show
    Post-market surveillance plan, with trend methods and thresholds.
  10. RequiredQualityRegulatory21 CFR Part 806[50]

    Know who decides and who reports before you need to.

    Read more
    Good practice
    Define who decides on corrections and removals, who reports them, and how you will find affected devices and customers.
    Rule of thumb
    Run a short tabletop exercise before launch. It’s cheaper than learning in a real recall.
    Common pitfalls
    No traceability to customers; unclear decision authority; reports filed late.
    Evidence to show
    Procedure for corrections and removals and the traceability approach.
  11. Added for your deviceRequiredRegulatory21 CFR 814.39, 814.84[51]

    Many changes to a PMA device need FDA approval before they’re made.

    Read more
    Good practice
    Set up the processes for annual reports and for deciding when a change needs a PMA supplement, before the first change arrives.
    Rule of thumb
    For a PMA device, assume a change needs FDA input until you show otherwise.
    Common pitfalls
    Changes made under internal change control without assessing supplement requirements.
    Evidence to show
    Procedures for PMA reports and supplements.
  12. RequiredOperationsQualityISO 13485 7.5.3, 7.5.4; 21 CFR 820.35(b)[1][44]

    A reusable display or handpiece needs a repair and loaner process on day one.

    Read more
    Good practice
    Set up servicing, repair and loaner processes for reusable or serviceable parts, with records, and decide which service events need evaluation as complaints.
    Rule of thumb
    Every service event is field data. Look at it.
    Common pitfalls
    Service handled by a separate team that never reports trends; repairs without records; no spare parts plan.
    Evidence to show
    Servicing procedure, service records template and the link to complaint handling.
  13. RequiredQualityISO 13485 5.6, 8.2.4, 8.5.2; 21 CFR 820.10; EU MDR Art. 10(9)[1][44][3][52]

    Under the QMSR, FDA can review management review and internal audit records.

    Read more
    Good practice
    Run an internal audit across the QMS, hold a management review before launch, make sure CAPA is working, and have the required certificate in place.
    Rule of thumb
    Find your own gaps before an auditor or investigator does.
    Common pitfalls
    First internal audit scheduled after launch; CAPA system set up but never used.
    Evidence to show
    Internal audit report, management review record, CAPA records and certificates.
  14. Added for your deviceRequiredR&DQualityIEC 62304 clauses 6, 9; FDA software change guidance[8][53]

    The first patch is usually needed sooner than planned.

    Read more
    Good practice
    Define how field problems are logged, evaluated for risk, fixed, verified and released, and how users are told.
    Rule of thumb
    Plan your first maintenance release before launch.
    Common pitfalls
    Hotfixes released without verification; problem reports not linked to complaints.
    Evidence to show
    Software maintenance plan and problem resolution records.
  15. Added for your deviceRequiredR&DQualityFD&C Act section 524B; EU MDR and IVDR Annex I[9][3][12]

    Required in US submissions for cyber devices (devices that include software, can connect to the internet and could be vulnerable to cybersecurity threats); EU Annex I also requires IT security for devices with software.

    Read more
    Good practice
    Monitor known vulnerabilities in your software and its components, disclose and patch in a coordinated way, and keep the software bill of materials current.
    Rule of thumb
    Your software bill of materials is only useful if someone checks it against new vulnerabilities.
    Common pitfalls
    An SBOM produced for the submission and never updated.
    Evidence to show
    Postmarket cybersecurity plan, SBOM and vulnerability management records.
  16. RequiredRegulatoryCommercialFD&C Act misbranding provisions; EU MDR Art. 7[3]

    Claims beyond the authorized intended use are a common launch-week mistake.

    Read more
    Good practice
    Review every promotional piece against the authorized intended use and indications, and keep records of approvals.
    Rule of thumb
    If the claim isn’t in the indications, it doesn’t go in the brochure.
    Common pitfalls
    Social media posts written by sales; trade-show demos showing unapproved uses; old materials still in circulation.
    Evidence to show
    Promotional review procedure and approval records.
  17. Added for your deviceRequiredRegulatoryEU MDR Art. 18[3]

    Patients keep the card, so its content has to be ready before the first implant.

    Read more
    Good practice
    Prepare the implant card and patient information with the required content, and plan how they reach the patient.
    Rule of thumb
    Check the card is readable by patients, not just accurate.
    Common pitfalls
    Cards not supplied with the device; information inconsistent with labeling.
    Evidence to show
    Implant card, patient information and their review records.
  18. Added for your deviceRequiredQuality21 CFR Part 821[54]

    FDA can order tracking for Class II or III devices whose failure would likely have serious adverse health consequences, or that are life-sustaining or life-supporting and used outside a device user facility.

    Read more
    Good practice
    Check whether FDA has ordered tracking for your device type, and if so set up the tracking system and records before launch.
    Rule of thumb
    If tracking applies, test that you can locate devices quickly.
    Common pitfalls
    Assuming distribution records meet tracking requirements.
    Evidence to show
    Tracking procedure and records.
  19. Good practiceCommercial

    The people customers call first need to know what counts as a complaint. See it go wrong in the case study below ↓

    Read more
    Good practice
    Train sales, customer service and clinical trainers on the device, the instructions for use, and how to recognise and log a complaint.
    Rule of thumb
    The first person a customer calls should know what to do with the call.
    Common pitfalls
    Training focused only on selling; no refresher when the instructions change.
    Evidence to show
    Training materials and records.
  20. RequiredOperationsISO 13485 8.2.6, 7.5.9[1]

    You should be able to find every shipped device or batch quickly.

    Read more
    Good practice
    Release inventory only after acceptance activities are complete, and make sure distribution records let you trace devices to customers.
    Rule of thumb
    You should be able to find every shipped unit of a batch quickly.
    Common pitfalls
    Shipping before release; distributor records you can’t access; returns not traced.
    Evidence to show
    Release records and distribution records.
  21. RequiredQualityISO 14971 clause 9[7]

    The review confirms the plan was carried out, overall residual risk is acceptable, and post-production methods are in place.

    Read more
    Good practice
    Review that the risk management plan was carried out, that overall residual risk is acceptable, and that methods to collect production and post-production information are in place, and approve the report.
    Rule of thumb
    The risk management report is the summary an auditor reads first. Make it stand on its own.
    Common pitfalls
    Report written as a formality; post-production information collection not actually set up.
    Evidence to show
    Approved risk management report.
  22. RequiredR&DQualityISO 13485 7.3.10[1]

    This is what the old FDA rules called the design history file, and auditors often ask for it first.

    Read more
    Good practice
    Keep the design and development file current through the project, with links to each record rather than copies.
    Rule of thumb
    If it takes more than a few minutes to show the evidence for a requirement, the file isn’t ready.
    Common pitfalls
    Files assembled the week before launch; missing records of design changes.
    Evidence to show
    Design and development file index with links to records.
  23. RequiredQualityISO 13485 7.3.9[1]

    From launch on, every change to the device goes through design change control.

    Read more
    Good practice
    Hold a launch review that confirms every check is done or has an accepted owner and date, and hand over to change control and post-market surveillance.
    Rule of thumb
    After launch, every change is a design change until you show otherwise.
    Common pitfalls
    Open items left without owners; changes made in the first weeks without going through change control.
    Evidence to show
    Launch review record and the handover to sustaining.

After the last gate

Launch is where NPI ends and two other processes take over. Every change to the device, its labeling, its suppliers or its manufacturing now goes through design change control, including a check on whether the change needs a new submission. And the post-market surveillance plan starts collecting the field data that will confirm, or challenge, the risk estimates made before launch.[1][3]

Hold a short retrospective a few weeks after the first shipment, while the details are fresh. Which checks were done late, which were done twice, and which were missing from this list? Fold the answers into your own gate template before the next project starts.

Case study

The Launch That Slipped Five Months

What happens when these checks are skipped? No single disaster delayed the Tavora. Eight ordinary problems did, each one small when it started, and together they pushed the launch back five months. Here is the launch, gate by gate: what happened, and which check would have caught it earlier.

The deviceTavora single-use flexible cystoscope, with a reusable handheld display
Planned US launchSeptember 2025
Actual US launchFebruary 2026
EU launchApril → July 2026

The Tavora, its team and its timeline are fictional. The problems are composites of failure patterns common in device launches, and the regulatory requirements cited are real.

The plan

The Tavora is a sterile, single-use scope for looking inside the bladder in a urology clinic, paired with a reusable handheld display that shows and records the image. Each scope is built by a contract manufacturer, packed in a sealed pouch, sterilized with ethylene oxide (EtO) and thrown away after one procedure. The display is charged, wiped down and used again.

That mix made the Tavora a typical new product introduction (NPI): electronics and software from the development team, a molded and bonded scope built by someone else, a sterile barrier and a shelf life to prove, labeling with unique device identifiers (UDIs), and a 510(k) in the US followed by CE marking in the EU. The plan gave each of those a lane, with a US launch in September 2025.

Here's how the plan and reality compare. The numbered markers match the sections below.

PlannedActual1Where it went wrong

Scroll sideways to see the whole timeline.

Planned and actual dates for the Tavora's main workstreams, January 2025 to August 2026. Select a marker to jump to that part of the story.

1 · January 2025 · Design freeze

The freeze that wasn't

The design freeze gate passed “with conditions.” Two items were still open: the adhesive for the scope's bending section, and the size of the sterile pouch. Neither looked serious. Both were written into the gate minutes, and neither had an owner or a due date.

The pouch was the one that hurt. In April, packaging engineering moved to a larger pouch so the scope's cable wouldn't kink. A sensible change, but the sterilization validation, the packaging validation and the shelf-life aging all depend on the final pouch, and none of them could start until it was settled. Nobody at the gate had asked what the open items could invalidate downstream.

What would have caught it

Treat every gate condition as a tracked action with an owner, a date and a list of what it could affect. If closing a condition could restart sterilization, packaging or aging work, it isn't a minor condition; it's a reason to hold the gate, or to start that work at risk with eyes open.

2 · March–July 2025 · Design validation

Validated on the wrong scopes

To save time, the team ran summative usability testing and its design validation on scopes hand-built in the engineering lab. The contract manufacturer's first production scopes arrived a month later, and urologists who tried them noticed straight away: the bending section was stiffer.

ISO 13485 requires design validation on product that represents production, such as early production units or an equivalent, and the team must record why its choice qualifies.[1] The team had no rationale that would stand up, because the units weren't equivalent. Part of the validation had to be repeated on production scopes, which cost five weeks.

What would have caught it

Decide at planning time which build each verification and validation activity will use, and write down why that build represents production. If the production process isn't ready, the honest choice is usually to wait, or to run the test early as a formative study and repeat the part that counts.

3 · May 2025 · Pilot build

A supplier change nobody announced

During the first pilot build, some scopes came out of sterilization with hazy edges on the image. It took three weeks to trace: the camera module supplier had switched the adhesive that holds the lens, a change it considered minor. The new adhesive didn't tolerate the EtO cycle as well as the old one.

The purchase agreement didn't require the supplier to report changes. Where it applies, ISO 13485 expects a written commitment from the supplier to warn the manufacturer before making any change that could affect whether its part still meets requirements.[1] Reverting the adhesive, requalifying the module and rebuilding the pilot lot took seven weeks in all.

What would have caught it

Rank suppliers by how much their part affects safety and performance, and put change notification into the agreements with the critical ones before the first pilot build, not after the first surprise. For the Tavora, the camera module, the bending section, the pouch and the contract sterilizer were all critical.

4 · June 2025 · Design transfer

Transfer treated as a handoff

The plan showed design transfer as a single box near the end: hand the drawings, specifications and test methods to the contract manufacturer, and start building. In practice, the leak test that checks every scope's seal failed its first gauge study on the manufacturer's line. It had been developed in the engineering lab on a different fixture, by the engineer who designed it.

ISO 13485 expects a team to show, before release, that its design outputs can be built to specification on the production line, and that the line can do it consistently.[1] A test method that only works in one person's hands isn't ready. Redesigning the fixture and repeating the study took three weeks, mostly hidden behind the supplier problem.

This kind of problem doesn't always stay hidden. When FDA reviewed 437 Class II recalls from October 2019 to September 2020, the most common root cause was process control: how devices are made, rather than how they were designed.[55]

What would have caught it

Run transfer as a thread through development, not a box at the end. Bring manufacturing and quality engineers in before design freeze, validate test methods on the production fixtures with the people who'll use them, and check the medical device file is complete as items are released, not all at once.[1]

5 · July–October 2025 · Sterilization and shelf life

Sterile, but for how long?

Because the pouch changed late (section 1), the EtO validation started two months behind plan. The first runs showed EtO residuals above the team's acceptance limits, which are based on ISO 10993-7.[28][32] The larger pouch and the denser shipping carton slowed aeration. Longer aeration fixed it, but the validation had to be partly repeated.

The shelf-life plan had a second problem. Accelerated aging, which uses heat to simulate time, can only start once the final product and sterile barrier exist. ASTM F1980 describes the method, and ISO 11607-1 accepts accelerated aging as evidence for the sterile barrier's expiry date while real-time aging continues. The device's own stability needs its own evidence.[33][14] With the late start, an aging temperature limited by the lens adhesive, and only the data in hand by the time of the 510(k) response, the team could support just a six-month expiry at launch instead of the planned two years. Nobody had told the commercial team, who had planned inventory around two years.

What would have caught it

Put sterilization, packaging validation and aging on the critical path from day one, and work out the expiry date you can support at launch from the date aging can start. Share that date with the commercial and supply chain teams; a short expiry changes how much stock to build and where to hold it.

6 · July 2025–January 2026 · 510(k)

Ninety days isn't three months

The plan assumed clearance three months after submission. FDA's review goal for a 510(k) is counted in FDA days, and the clock stops while a submission is on hold waiting for answers.[56] The Tavora went on hold about two months into review, with an additional information request covering EtO residuals and software documentation. A submission on hold has 180 calendar days to respond; the team took eleven weeks, partly because the repeated sterilization work in section 5 meant new residual data had to be generated.[56]

Clearance came in mid-January 2026, and the first commercial shipment left in February. Until clearance, the team could build inventory but couldn't sell or ship it commercially.

What would have caught it

Plan launches around a realistic clearance range, not the review goal. Assume at least one round of questions, and have the evidence most likely to draw them, such as sterilization, biocompatibility, software and cybersecurity, reviewed by someone outside the project before you submit.

7 · February–March 2026 · US launch

Ready to ship, not ready to support

In the first week, three clinics called about the display freezing mid-procedure. The calls went to sales, who treated them as tech support: they talked the clinics through a restart and moved on. The complaint handling procedure had been written with the single-use scope in mind and didn't mention the display at all.

The gap surfaced a month later, in an internal audit. Every one of those calls should have been logged and evaluated as a complaint, including whether it needed a medical device report.[1][44][49] They were logged late, investigated (a firmware timing fault) and judged not reportable, but the late records became an audit finding.

What would have caught it

Make post-market readiness part of the launch gate, with the same weight as inventory. Before the first shipment, everyone who talks to customers should know what counts as a complaint and where it goes, and the procedure should cover every part of the system, including accessories and reusable components.

8 · April–July 2026 · EU launch

A regulatory assumption that went out of date

The EU launch slipped behind the US one while the notified body finished its review. By the time the certificate arrived, the rules had changed under the plan's feet. Since 28 May 2026, the first four EUDAMED modules have been mandatory, and a new device must be registered in EUDAMED before the first unit is placed on the EU market. There's no transition period for new devices.[48][3]

The launch plan, written in 2024, had assumed registration could follow later. Registering the device in EUDAMED, with its Basic UDI-DI and UDI-DI data, added three weeks before the first EU shipment in July.

What would have caught it

Re-check regulatory assumptions at every gate, not just at the start. A launch plan can easily outlive the rules it was written under, as US teams also found when the QMSR replaced the old quality system regulation on 2 February 2026.[57]

What added up to five months

None of the eight problems was a delay of five months on its own. They stacked: an open condition at design freeze moved the pouch, the pouch moved sterilization, sterilization moved the submission and the expiry date, and the hold moved clearance. Meanwhile, the supplier and test method problems ate the slack that might have absorbed the rest.

In their retrospective, the team agreed on a short list of changes for the next product:

Gate conditions are actions

Each one gets an owner, a date and an impact check, and the next gate starts by closing them.

Plan the builds

Decide which build each verification and validation activity uses, and why it represents production.

Critical suppliers first

Change notification and quality agreements are in place before the first pilot build.

Transfer starts early

Manufacturing owns test methods and fixtures from design freeze, and the medical device file grows as items are released.

Sterile and stable on the critical path

Packaging is frozen first, and the launch expiry date is agreed with commercial teams early.

Clearance is a range

Launch dates assume a round of questions, not the review goal.

Support is part of launch

Complaint handling covers every component and every person who talks to customers, before the first shipment.

Re-check the rules

Each gate confirms the regulatory assumptions are still current in every market.

Questions worth asking at your next gate review

Copy these into your gate template and see how many your team can answer with evidence, not opinion. For the full list, use the gate-by-gate checklist above.

  1. Which open items are we accepting as conditions, and what work could each one restart?
  2. Which build will each remaining verification and validation activity use, and why does it represent production?
  3. Do our critical suppliers have to tell us about changes before they make them?
  4. Has every test method been validated on the production fixture, by the people who'll run it?
  5. What expiry date can we support at launch, and do the commercial and supply chain teams know it?
  6. What clearance range are we planning around, and what happens to the launch if we get questions?
  7. Does complaint handling cover every component, and does everyone who talks to customers know how to log one?
  8. Which regulatory assumptions in this plan have changed since we wrote it?

References

  1. ISO 13485:2016, Medical devices — Quality management systems — Requirements for regulatory purposes. Incorporated by reference into 21 CFR Part 820 since 2 February 2026. www.iso.org/standard/59752.html
  2. 21 CFR Part 807 (establishment registration and device listing; Subpart E, premarket notification), Part 814 (premarket approval) and Part 860 Subpart D (De Novo classification). www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-807
  3. Regulation (EU) 2017/745 on medical devices (EU MDR), including Articles 1, 7–11, 13–15, 18–20, 25, 27–29, 31–32, 51–52, 61–62, 84–89 and 117, and Annexes I–III and XIV. eur-lex.europa.eu/eli/reg/2017/745/oj
  4. U.S. FDA, CLIA Categorizations. www.fda.gov/medical-devices/ivd-regulatory-assistance/clia-categorizations
  5. U.S. FDA, Requests for Feedback and Meetings for Medical Device Submissions: The Q-Submission Program, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/requests-feedback-and-meetings-medical-device-submissions-q-submission-program
  6. IEC 62366-1:2015+AMD1:2020, Medical devices — Part 1: Application of usability engineering to medical devices. webstore.iec.ch/en/publication/67220
  7. ISO 14971:2019, Medical devices — Application of risk management to medical devices. www.iso.org/standard/72704.html
  8. IEC 62304:2006+AMD1:2015, Medical device software — Software life cycle processes. webstore.iec.ch/en/publication/22790
  9. U.S. FDA, Cybersecurity in Medical Devices: Quality Management System Considerations and Content of Premarket Submissions, final guidance, February 2026 (section 524B of the FD&C Act, cyber devices). www.fda.gov/regulatory-information/search-fda-guidance-documents/cybersecurity-medical-devices-quality-management-system-considerations-and-content-premarket
  10. Regulation (EU) 2024/1689 laying down harmonised rules on artificial intelligence (AI Act), as amended by Regulation (EU) 2026/1744. eur-lex.europa.eu/eli/reg/2024/1689/oj
  11. 21 CFR Part 812, Investigational device exemptions. www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-812
  12. Regulation (EU) 2017/746 on in vitro diagnostic medical devices (EU IVDR). eur-lex.europa.eu/eli/reg/2017/746/oj
  13. IEC 60601-1-11, Medical electrical equipment — Requirements for medical electrical equipment and medical electrical systems used in the home healthcare environment.
  14. ISO 11607-1:2019+Amd 1:2023, Packaging for terminally sterilized medical devices — Part 1: Requirements for materials, sterile barrier systems and packaging systems. www.iso.org/standard/70799.html
  15. ISO 10993-1:2025, Biological evaluation of medical devices — Part 1: Requirements and general principles for the evaluation of biological safety within a risk management process, November 2025. www.iso.org/standard/84512.html
  16. U.S. FDA, Testing and Labeling Medical Devices for Safety in the Magnetic Resonance (MR) Environment, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/testing-and-labeling-medical-devices-safety-magnetic-resonance-mr-environment
  17. ASTM F2503, Standard Practice for Marking Medical Devices and Other Items for Safety in the Magnetic Resonance Environment.
  18. IEC 60601-1:2005+AMD1:2012+AMD2:2020, Medical electrical equipment — Part 1: General requirements for basic safety and essential performance, and IEC 60601-1-2:2014+AMD1:2020 (electromagnetic disturbances). webstore.iec.ch/en/publication/67497
  19. Directive 2011/65/EU on the restriction of hazardous substances in electrical and electronic equipment (RoHS). eur-lex.europa.eu/eli/dir/2011/65/oj
  20. Directive 2012/19/EU on waste electrical and electronic equipment (WEEE). eur-lex.europa.eu/eli/dir/2012/19/oj
  21. Regulation (EU) 2023/1542 concerning batteries and waste batteries. eur-lex.europa.eu/eli/reg/2023/1542/oj
  22. 49 CFR 173.185, Lithium cells and batteries (including the UN 38.3 test summary). www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-C/part-173/subpart-E/section-173.185
  23. Directive 2014/53/EU on radio equipment (RED). eur-lex.europa.eu/eli/dir/2014/53/oj
  24. 47 CFR Part 2, Subpart J, Equipment authorization procedures, and § 2.803 (marketing of radio frequency devices prior to authorization). www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-2/subpart-I/section-2.803
  25. U.S. FDA, Radio Frequency Wireless Technology in Medical Devices, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/radio-frequency-wireless-technology-medical-devices-guidance-industry-and-fda-staff
  26. IEC 82304-1:2016, Health software — Part 1: General requirements for product safety. webstore.iec.ch/en/publication/26120
  27. Regulation (EC) No 1907/2006 (REACH), Article 33. eur-lex.europa.eu/eli/reg/2006/1907/oj
  28. ISO 11135:2014+Amd 1:2018, Sterilization of health-care products — Ethylene oxide — Requirements for the development, validation and routine control of a sterilization process for medical devices. www.iso.org/standard/56137.html
  29. ISO 11137-1:2025, Sterilization of health care products — Radiation — Part 1: Requirements for the development, validation and routine control of a sterilization process for medical devices.
  30. ISO 17665:2024, Sterilization of health care products — Moist heat — Requirements for the development, validation and routine control of a sterilization process for medical devices.
  31. ISO 11737-1, Sterilization of health care products — Microbiological methods — Part 1: Determination of a population of microorganisms on products.
  32. ISO 10993-7:2026, Biological evaluation of medical devices — Part 7: Ethylene oxide sterilization residuals. It replaced the 2008 edition in April 2026; the case study, set in 2025, used the 2008 edition. www.iso.org/standard/84824.html
  33. ASTM F1980-21, Standard Guide for Accelerated Aging of Sterile Barrier Systems and Medical Devices. store.astm.org/f1980-21.html
  34. U.S. FDA, Reprocessing Medical Devices in Health Care Settings: Validation Methods and Labeling, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/reprocessing-medical-devices-health-care-settings-validation-methods-and-labeling
  35. ISO 17664-1:2021, Processing of health care products — Information to be provided by the medical device manufacturer for the processing of medical devices — Part 1: Critical, semi-critical and non-critical medical devices. www.iso.org/standard/81720.html
  36. 21 CFR Part 801, Labeling. www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-801
  37. ISO 15223-1:2021, Medical devices — Symbols to be used with information to be supplied by the manufacturer — Part 1: General requirements.
  38. Commission Implementing Regulation (EU) 2021/2226 on electronic instructions for use of medical devices, as amended by Implementing Regulation (EU) 2025/1234 (applies to devices under the MDR). eur-lex.europa.eu/eli/reg_impl/2021/2226/oj
  39. U.S. FDA, eSTAR Program. www.fda.gov/medical-devices/how-study-and-market-your-device/estar-program
  40. U.S. FDA, Medical Device User Fee Amendments (MDUFA), including small business determination. www.fda.gov/industry/fda-user-fee-programs/medical-device-user-fee-amendments-mdufa
  41. U.S. FDA, Marketing Submission Recommendations for a Predetermined Change Control Plan for Artificial Intelligence-Enabled Device Software Functions, final guidance, December 2024, updated August 2025 (FD&C Act section 515C). www.fda.gov/regulatory-information/search-fda-guidance-documents/marketing-submission-recommendations-predetermined-change-control-plan-artificial-intelligence
  42. Global Harmonization Task Force, SG3/N99-10:2004, Quality Management Systems — Process Validation Guidance (hosted by IMDRF). www.imdrf.org/sites/default/files/docs/ghtf/final/sg3/technical-docs/ghtf-sg3-n99-10-2004-qms-process-guidance-04010.doc
  43. ISO 14644-1, Cleanrooms and associated controlled environments — Part 1: Classification of air cleanliness by particle concentration.
  44. 21 CFR Part 820, Quality Management System Regulation: § 820.35 (control of records) and § 820.45 (device labeling and packaging controls). www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-820
  45. 21 CFR 809.10, Labeling for in vitro diagnostic products. www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-809
  46. U.S. FDA, Unique Device Identification System (UDI System): 21 CFR 801.20 and Part 830, including the Global Unique Device Identification Database (GUDID). www.fda.gov/medical-devices/device-advice-comprehensive-regulatory-assistance/unique-device-identification-system-udi-system
  47. Federal Food, Drug, and Cosmetic Act sections 801(e) and 802 (21 U.S.C. 381(e), 382), export of devices. uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title21-section382
  48. Health Products Regulatory Authority (Ireland), Mandatory use of EUDAMED modules for medical devices. www.hpra.ie/news-events/news/article/mandatory-use-of-eudamed-modules-for-medical-devices
  49. 21 CFR Part 803, Medical Device Reporting, including § 803.17 (written MDR procedures). www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-803
  50. 21 CFR Part 806, Medical devices; reports of corrections and removals. www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-806
  51. 21 CFR Part 814, Premarket approval of medical devices, including § 814.39 (PMA supplements) and § 814.84 (reports). www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-814
  52. U.S. FDA, Quality Management System Regulation: Frequently Asked Questions. www.fda.gov/medical-devices/quality-management-system-regulation-qmsr/quality-management-system-regulation-frequently-asked-questions
  53. U.S. FDA, Deciding When to Submit a 510(k) for a Software Change to an Existing Device, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/deciding-when-submit-510k-software-change-existing-device
  54. 21 CFR Part 821, Medical device tracking requirements. www.ecfr.gov/current/title-21/chapter-I/subchapter-H/part-821
  55. U.S. FDA, Office of Medical Device and Radiological Health Operations, Recalls presentation (Class II recall analysis, October 2019–September 2020), OMDRHO virtual conference, 23 June 2021. www.fda.gov/media/150413/download
  56. U.S. FDA, FDA and Industry Actions on Premarket Notification (510(k)) Submissions: Effect on FDA Review Clock and Goals, guidance for industry and FDA staff. www.fda.gov/regulatory-information/search-fda-guidance-documents/fda-and-industry-actions-premarket-notification-510k-submissions-effect-fda-review-clock-and-goals
  57. U.S. FDA, Medical Devices; Quality System Regulation Amendments, final rule, Federal Register 89 FR 7496, 2 February 2024 (effective 2 February 2026). www.federalregister.gov/documents/2024/02/02/2024-01709/medical-devices-quality-system-regulation-amendments

The Tavora, its team and its timeline are fictional and do not describe any real product or company. This checklist is general guidance, not legal or regulatory advice. Gate names and the order of items are illustrative; adapt them to your own procedures, device type and markets. Requirements are paraphrased; check the current text of each standard and regulation before relying on it.